Construction of the I-495 Virginia HOT Lanes is divided into four areas:

Beltway North of I-66 Interchange/Tysons Corner/McLeanView Details »



I-66 Interchange/MerrifieldView Details »



Beltway South of I-66 InterchangeView Details »



Springfield InterchangeView Details »

Construction in this area includes the continuation of the Springfield Interchange Improvement Project. Improvements to the Springfield Interchange will provide a seamless integration with HOV service on I-95/395 and the Capital Beltway once HOT lanes construction is complete.



General HOT Lanes Schedule

2007 - 2009
Design and Engineering

2008
Aerial Study

Spring 2008
Design Public Hearing

2008 - 2010
Right of Way Activity

2008 - 2009
Cleaning and Grubbing

2008 - 2010
Utility Relocation

2008 - 2011
Soundwall Relocation / Construction

2008 - 2012
Bridge Construction